Creating patch change requests
For organizations that require approvals, open a change request to request a patch deployment to resolve identified vulnerabilities.
You can create change request from various locations:
-
Patch Update form: Can request to deploy a single patch to multiple devices
-
Discovered Item form: Can request to deploy a single patch to a single device
-
Remediation Task form: Can request to deploy the preferred patches defined in the task to one or more devices
Create patch change request from a Patch Update form
- In ServiceNow, go to the filter navigator and type Tanium VR Patch Orchestration.
- Go to .
- In the Number column, click the patch that you want to schedule.
- Click Create Change and complete the Fields for creating a patch change request in the Patch Deployment section.
- At the end of the form, click Create Change.
Create patch change request from a Discovered Item form
- In ServiceNow, go to the filter navigator and type Tanium VR Patch Orchestration.
- Go to .
- In the Number column, click the device that you want to patch.
- Click Create Change and complete the Fields for creating a patch change request in the Patch Deployment section.
- At the end of the form, click Create Change.
Create patch change request from a Remediation Task form
- In ServiceNow, go to the filter navigator and type Tanium VR Patch Orchestration.
- Go to or Assigned to My Group.
- In the Number column, click a remediation task. If the task includes preferred patches, the Create Change button is visible.
- Click Create Change and complete the Fields for creating a patch change request in the Patch Deployment section.
- At the end of the form, click Create Change.
Fields for creating a patch change request
-
Deployment Name: Enter a name to help you track this deployment.
-
Patch update: Select the patch to deploy.
-
Deployment type: Select a type.
-
Available time: Set the value for the time the patch becomes available.
-
Deadline: Set the value for the time the patch is last available for deployment.
-
Start Time and End Time: Enter the start and end times for the time window. Enter when you want the patch to start its deployment and enter the last day that the patch can be installed.
-
Allow restart: Select this option to instruct the machines in the group to restart automatically after the patch is successfully completed.
-
Deployment time based on: Select a time zone from the list to base your deployment time window on.